The SMA permit for the section of the
path between Lydgate and Lihi parks was approved in 2007, with the
condition that “Applicant shall commence construction of the
proposed project within 2 years from the date of Planning Commission
approval of this Special Management Area permit, and complete
construction within 4 years.”
Now an ordinary person would read that
as construction should have begun by 2009 and be pau by
2011, which it wasn't. The county, however, is saying no, that language means 2 + 4,
or six years to complete. So what? Is the county now going to give every
other developer similar latitude?
Further, the permit was approved when
the plan was for a boardwalk on the beach. The design has been
changed substantially to a concrete path alongside the highway, which
should have triggered another review by the Planning Commission. But
the last thing the county wants is to reopen the public process.
Instead, it's setting a terrible
example by building public infrastructure too
close to the ocean through use of a shoreline setback variance. It's also
armoring the coastline through its use of concrete — please don't
tell me a concrete foot path attached to a 3.5-foot thick wall isn't a
seawall — and intensive vegetation.
At least, it sure sounds like intensive
vegetation, when you consider they're spending $4,000 on beach
heliotrope and another $4,000 on hala, all in 25-gallon pots. No
quantity is specified, which would make it awfully hard to determine
whether the supplier actually fulfilled the contract. Another $10,000
is allocated for 1-gallon pots of naupaka, again with no quantity
specified.
Then there's $15,000 for grass seed
that is apparently mixed with gold dust at that price in addition to $6,000 for
hydromulch seeding. Though why we would want to put a chemical
concoction that close to the ocean is beyond me.
Take a gander through the rest of the budget. (Scroll to the end of the document.) Some $584,000 is being spent on concrete, and $145,000 for
reinforcing steel. That's to make sure if you hit that wall with your
car, it's guaranteed to be a big smashup. Another $230,000 is
budgeted for rock facing on the concrete wall. Additionally, $42,500 is
earmarked for cops and other traffic controls, with $25,000 allocated
for archaeological monitoring. The pavement markers are $8,000,
though it's hard to know exactly what we're paying for, as again, no specific quantities are listed.
Some $13,000 is budgeted for signs alone –
gee, who would've thought a mile marker sign cost $1,500?
Which makes me wonder how much the sign
cost that was put up right in the middle of Kuhio Highway — and run
over within a day — advising motorists of the new crosswalk that's
been installed between Kawaihau and Hauaala roads, one of the most
congested sections in Kapaa. The crosswalk was painted so
people could get from the Kawaihau spur, which is not yet pau, to
the coastal Path.
Yet for some reason the county says, no, we can't
possibly have the Path crossing the highway at either Safeway or
Kuamoo Road, both of which have crosswalks and traffic signals. What's up with that? Like so much of the Path "planning," it's all rather ad hoc and opaque.
Meanwhile, a reader sent a photo
showing how broad Wailua Beach was in 1981. The county keeps claiming it's accreting — a fancy word for growing — but we all know it hasn't been
this wide for decades.
Two questions remain: why are Mayor
Bernard Carvalho Jr., Lenny Rapozo, Doug Haigh and Thomas Noyes
hellbent on this expensive, destructive and foolhardy
course? And what will it take to stop this madness before it's too
late for what's left of Wailua Beach?